From:                                         Development Control (DMW)

Subject:                                     FW: Newhaven PAR - Out of Hours Working

 

From: Edward Sheath
Sent: 07 August 2020 1:15 PM
To:
Cc: Development Control (DMW); Sarah Iles
Subject: RE: Newhaven PAR - Out of Hours Working

 

Dear Michael,

 

I refer to the e-mail you sent to Sarah on Wednesday, which sought approval for out of hours working in respect of the Newhaven Port Access Road (planning application ref: LW/2565/CC). I am responding to this request as Sarah is on leave this week.

 

I have given due consideration to your request and taken into account the nature of the works proposed and the potential impact of the works on the amenity of the local community. Whilst these works are proposed to be carried out during what are considered to be particularly unsociable hours, this has to be balanced against the necessity to undertake the works during railway possessions (in respect of the works proposed between the 10 and 15 August) and when traffic levels are light (in respect of the works between the 17 and 29 August). Consequently, in accordance with the powers delegated to me and pursuant to the provisions within Condition 17 of the above planning permission, I hereby APPROVE the additional hours of working as set out in your email of the 5 August.  This is on the basis that the works are undertaken in accordance with the details set out in your aforementioned e-mail, and in particular the mitigation measures proposed.

 

Please note that if at any time the activities being carried out in these extended hours give rise to justifiable complaint, or demonstrable harm to amenity, I reserve the right to withdraw this temporary amendment to the permitted working hours. Please also note that should you receive any complaints, you should notify the County Planning  Authority within two working days of receiving the complaint.

 

Kind Regards,

 

Edward Sheath

Head of Planning and Environment

Communities, Economy and Transport


eastsussex.gov.uk

                                                                                        ESCC_logos-TO-USE-90x64px

 

 

 

From: Astley-Heilbronn, Michael

 

Sent: 05 August 2020 15:28
To: Sarah Iles >
Cc: Buckle, >; Walker, Ian <; Snook, Sam >; Kinnell, Derren >; Bob Pape >; Mark Andrew Subject: Newhaven PAR - Out of Hours Working

 

Sarah,

 

Good Afternoon, hope you are well

 

Town and Country Planning Act 1990 relating to Newhaven Port Access Road, reference LW/2565/CC – Condition 17

 

We are writing to request out of hours working in relation to the Newhaven Port Access Road Project. The out of hours working relates to the following works:-

 

  1. Painting remedial works to the outside of the beam sections across the railway.

 

We are planning our works in consultation with Network Rail during the following times:-

 

 

 

The painting remedial works are required following the removal of the temporary shutters over the railway. The works will involve cleaning the girders and applying the 3 coat paint system to the beams where some minor damage has been sustained. All access to the beams will be from a mobile elevated platform from the newly constructed bridge deck.

 

The works are required during a night time railway possession so that the required construction plant can carry out operations safely and to prevent any risks to the operational railway.

 

To minimise impact on the local community we propose the following mitigation:

 

 

The main plant and equipment planned for the works are:

 

 

There are 9 No. planned personnel for the works:

 

 

The works will be accessed from our south compound currently located within Newhaven Port and within our current site footprint of the Newhaven Port Access Road Scheme.

 

2.         Kerb realignment works Mckinley Way, Drove Retail Park.

 

We are planning our works in consultation with ESCC Highway’s team.

 

As part of our works for the Newhaven PAR project we are required to carry out some minor kerb amendments and relocate the existing tactile crossing (see attached drawing 6000032-WSP-HKF-NPAR-DR-CH-0003) to the entrance of the Drove Retail Park of off Mckinley Way. The entrance is shown below.

 

 

Due to the location and volume of traffic using the retail park during normal working hours we intend to complete these works between 20.00hrs – 06.00hrs using Traffic management priority boards over a period of two weeks when minimal traffic is entering the retail park.

 

 

The works are required during off peak and night time periods so that the required construction plant can carry out operations safely and to prevent any traffic delays during the normal working hours for the retail park.

 

To minimise impact on the local community we propose the following mitigation:

 

 

The main plant and equipment planned for the works are:

 

 

There are 6 No. planned personnel for the works:

 

 

The works will be accessed from our North compound currently located at the end of Mckinley Way and within our current site footprint of the Newhaven Port Access Road Scheme.

 

In order to keep the public advised of our works an advance memo will be placed on our information boards positioned around the works explaining the works, with contact details of the site team should further questions arise from the general public regarding the works.

 

This application is made on behalf of the Assistant Director, Operations, East Sussex County Council and the relevant cost code for payment of fees due is C.5.13.067.2.

 

We trust that our proposals meet with your approval.

 

Enc.

Dwg 6000032-WSP-SBR-DR-CB-001 General Arrangement Drawing

Dwg 6000032-WSP-HKF-DR-CH-003 Kerbs, Footways and paved areas

 

Regards,

Mike

 

Michael Astley-Heilbronn BEng(Hons) CEng MICE | Senior Site Agent | BAM Nuttall Ltd

 

Site: BAM Nuttall Site Compound, c/o Newhaven Port Authority, East Quay, Newhaven, East Sussex, BN9 0BN

Office:Tenacre Court, Ashford Road, Harrietsham, Maidstone, Kent. ME17 1AH

 

Follow us…Image result for bam nuttall logoImage result for facebook logocid:image009.png@01D2BCE3.FFACD2C0cid:image014.png@01D2BCE3.FFACD2C0Image result for instagramImage result for youtube logo

 

email%20signature%20banner%202020

 

 

 

This message and its contents are subject to copyright and the information in it is confidential. It is intended solely for the addressee(s) and may contain privileged information. Its unauthorised use, disclosure, storage or copying is not permitted. If you are not the intended recipient, please inform the sender by return and destroy all copies of it.

Contracts may not be concluded on behalf of BAM Nuttall by means of e-mail communications and the author of this message is not authorised to conclude any contract on behalf the company by e-mail.

BAM Nuttall Limited Registered office St James House, Knoll Road, Camberley, Surrey GU15 3XW Registered number 305189 Registered in England and Wales